Heilsbronn, Unterulsenbach, Aurachtal, Großhabersdorf

31.5 MW portfolio for WWS-Projektbau

x-headline
Heilsbronn, Unterulsenbach, Aurachtal, Großhabersdorf
x-headline
31,5 MW
x-headline
2020

In 2020, maxsolar was able to design four communal solar energy plants for the project developer WWS Projektbau in Markt Erlbach and construct them as a general contractor and engineering service provider. Commissioning was carried out with the system being certificated in accordance with the new VDE 4110.

The ground-mounted plants in Heilsbronn (10 MW) and Großhabersdorf (10 MW) went into operation in the third quarter of 2020, with the other plants in Aurachtal (1.5 MW) and Unterulsenbach (10 MW) following in the last quarter of 2020.